Before and After at the Circle K on Foothills
Take a look at this before and after pic!
We're amazed by the progress at the Circle K on Foothills in Spokane. Over the course of 3 weeks, the following work has been completed:
→ Fuel tanks have been backfilled
→ Fuel pipes and sump set in gas island
→ Sewer pipes installed
→ Reclaim tanks, storm piping, and drywells brought onsite for install
→ Plumbing rough-in started on c-store
Keep checking back for updates on this project!